This Modification was raised by GTC on 2nd July 2014. The Proposal will be reviewed at the July Modification Panel meeting.
The Panel agreed that the Modification should proceed to development by workgroup.
The Workgroup Report was presented to the Panel on 20th August 2014. The Panel agreed to circulate for consultation.
The DMR was circulated for consultation on 26th August 2014 with a close out date of 16th September 2014.
The FMR was published on 24th September 2014 for consideration at the Panel meeting on 15th October 2014.
The Panel on 15th October 2014 recommended the Implementation of IGT063 with an Implementation Date of 1st October 2015. The FMR was sent to Ofgem for Authority Decision on 17th October 2014.
On 11th November 2014, Authority Decision was received to implement IGT063 on 1st October 2015.
Document Title | Description | Type | Pub Date | Author |
IGT063 | Authority Decision | Adobe PDF | 12/11/2014 | |
IGT063 | Final Modification Report to Ofgem | Adobe PDF | 17/10/2014 | |
IGT063 | Final Modification Report | Adobe PDF | 24/09/2014 | |
E.ON UK | DMR Response | Adobe PDF | 17/09/2014 | |
Fulcrum | DMR Response | Adobe PDF | 17/09/2014 | |
npower | DMR Response | Adobe PDF | 17/09/2014 | |
Indigo Pipelines | DMR Response | Adobe PDF | 17/09/2014 | |
IGT063 | Draft Modification Report | Adobe PDF | 26/08/2014 | |
IGT063 | Workgroup Report | Adobe PDF | 13/08/2014 | |
IGT063 | Final Modification Proposal | Adobe PDF | 13/08/2014 | |
IGT063 | Final Terms of Reference | Adobe PDF | 13/08/2014 | |
IGT063 | WG01 Agenda | Adobe PDF | 06/08/2014 | |
IGT063 | WG Terms of Reference | Adobe PDF | 06/08/2014 | |
IGT063 | Amended Modification Proposal (v1.1) | Adobe PDF | 01/08/2014 | |
IGT063 | Modification Proposal | Adobe PDF | 02/07/2014 |