- Raised by ES Pipelines on 10th August 2016
- Panel consideration on 17th August 201
- Work Group concluded 6th September 2016
- Panel considered Work Group report on 21st September 2016
- Draft Modification Report published 23rd September 2016
- DMR consultation closes 14th October 2016
- Consultation responses published 17th October 2016
- Final Modification Report (Pre Panel) published 18th October 2016
- Panel Decision 16th November 2016
- Final Modification Report (Post Panel) Published 18th November 2016
- The Panel accepted the Final Modification Report on 18th November, with all parties supporting the Implementation.
- IGT088 is to be implemented on the 23rd February 2017 IGT UNC Code release.
Document Title | Description | Type | Pub Date | Author |
IGT088 | Final Modification Report (Post Panel) | Adobe PDF | 18/11/2016 | Code Administrator |
IGT088 | Final Modification Report (Pre Panel) | Adobe PDF | 18/10/2016 | Code Administrator |
IGT088 | DMR Consultation Responses ZIP | Zip Archive | 18/10/2016 | Code Administrator |
IGT088 | Notice of Implementation | Adobe PDF | 01/12/2016 | Code Administrator |
IGT088 | DMR Consultation Response | Adobe PDF | 17/10/2016 | SSE Supply |
IGT088 | DMR Consultation Response | Adobe PDF | 17/10/2016 | Scottish Power |
IGT088 | DMR Consultation Response | Adobe PDF | 17/10/2016 | E-ON |
IGT088 | Draft Modification Report | Adobe PDF | 23/09/2016 | Code Administrator |
IGT088 | Workgroup Report | Adobe PDF | 14/09/2016 | Code Administrator |
IGT088 | Initial Modification Proposal | Adobe PDF | 10/08/2016 | Code Administrator |