Modification raised by Brookfield Utilities | 7th October 2015 |
Modification Proposal considered by Panel | 21st October 2015 |
The Modification Panel sent IGT082 to Workgroup for further development.
Workgroup #1 | 3rd November 2015 |
Workgroup #2 | 1st December 2015 |
The Workgroup Report was published on 9th December 2015 ahead of consideration at the Panel on 16th December 2015.
The Panel on 16th December determined that the Modification should be circulated as a Draft Modification Report.
The DMR was circulated for consultation on 17th December 2015.
Responses to the consultation was considered by the Panel on 20th January 2016. The Panel recommended implementation. The Final Mod Report was sent to Ofgem on 22nd January 2016.
Ofgem determined to NOT IMPLEMENT this Modification, with the Authority Decision received on 30th June 2016.
Document Title | Description | Type | Pub Date | Author |
IGT082 | Authority Decision | Adobe PDF | 01/07/2016 | |
IGT082 | Final Modification Report to Ofgem | Adobe PDF | 22/01/2016 | |
IGT082 | Notice of Non-Implementation | Adobe PDF | 01/07/2016 | |
IGT082 | Final Modification Report | Adobe PDF | 14/01/2016 | |
Brookfield Utilities | DMR Consultation Response | Adobe PDF | 14/01/2016 | |
EON UK | DMR Consultation Response | Adobe PDF | 14/01/2016 | |
Indigo Pipelines | DMR Response | Adobe PDF | 14/01/2016 | |
npower | DMR Response | Adobe PDF | 14/01/2016 | |
SSE Supply | DMR Response | Adobe PDF | 14/01/2016 | |
IGT082 | Draft Modification Report | Adobe PDF | 17/12/2015 | |
IGT082 | IGT082 Workgroup Report | Adobe PDF | 09/12/2015 | |
IGT082 | Single Service Provision Supporting Report | Adobe PDF | 27/11/2015 | |
IGT082 | Rationale for NEDs | Adobe PDF | 27/11/2015 | |
IGT082 | Revised Modification Proposal (v2.2) | Adobe PDF | 20/11/2015 | |
IGT082 | Terms of Reference | Word Document (Office 97-2003) | 03/11/2015 | |
IGT082 | Change of Supplier and SPR update timeline for October 2016 implementation dates | Adobe PDF | 12/10/2015 |