The Modification was raised by npower on the 27th September 2012.
The Draft Final Modification Report for this Modification was release for consultation on 16th January 2013 and was considered at the February 2013 Modification Panel Meeting.
The Final Modification Report can be seen below as well as Ofgem’s decision. An implementation date has been set for the 1st November 2013.
Document Title | Description | Type | Pub Date | Author |
IGT049 | Final Modification Report | Adobe PDF | 22/02/2013 | |
IGT049 | Authority Decision | Adobe PDF | 03/04/2013 | |
IGT049 | Draft Final Modification report | Adobe PDF | 16/01/2013 | |
Npower | DMR Consultation Response | Adobe PDF | 21/12/2012 | |
IPL | DMR Consultation Response | Adobe PDF | 21/12/2012 | |
IGT049 | Amended Ancillary Document | Adobe PDF | 30/11/2012 | |
IGT049 | Draft Modification Report | Adobe PDF | 30/11/2012 | |
Npower | Consultation Response | Adobe PDF | 12/11/2012 | |
Scottish Power | Consultation Response | Adobe PDF | 12/11/2012 | |
ESP | Consultation Response | Adobe PDF | 12/11/2012 | |
SSE Pipelines | Consultation Response | Adobe PDF | 12/11/2012 | |
E.On | Consultation Response | Adobe PDF | 09/11/2012 | |
British Gas | Consultation Response | Adobe PDF | 09/11/2012 | |
GTC Pipelines Ltd | Consultation Response | Adobe PDF | 29/10/2012 | |
Fulcrum Pipelines | Consultation Response | Adobe PDF | 22/10/2012 | |
IGT049 | Modification Proposal | Adobe PDF | 28/09/2012 |