IGT048 – Estimated Opening Meter Reads Code Amendment

The Modification was raised by npower on the 13th July 2012.

The Modification was considered at the August 2012 Modification Panel, where the Panel agreed to send it to consultation.

The Draft Final Modification Report for this Modification Proposal was sent out for consultation on 12th November 2012. The DFMR was considered at November’s Modification Panel, were the Panel recommended implementation.

Ofgem approved the Final Modification Report on 20th December 2012.

This Modification Proposal was implemented on 28th June 2013.

Document Title Description Type Pub Date Author
IGT048 Authority Decision Adobe PDF 20/12/2012  
IGT048 Final Modification Report Adobe PDF 22/11/2012  
IGT048 Draft Final Modification Report Adobe PDF 12/11/2012  
Fulcrum Pipelines DMR Consultation Response Adobe PDF 02/10/2012  
IGT048 Draft Modification Report Adobe PDF 01/10/2012  
IGT048 Modification Proposal Adobe PDF 17/08/2012  
Independent Pipelines Limited Consultation response Adobe PDF 11/09/2012  
GTC Consultation Response Adobe PDF 19/09/2012  
British Gas Consultation response Adobe PDF 10/09/2012  
Npower Consultation response Adobe PDF 10/09/2012  
Scottish Power Consultation response Adobe PDF 10/09/2012  
ESP Consultations response Adobe PDF 10/09/2012  
E.On Consultation response Adobe PDF 10/09/2012  
EDF Consultation response Adobe PDF 10/09/2012  
SSE Pipelines Consultation response Adobe PDF 10/09/2012  
SSE Supply Consultation response Adobe PDF 10/09/2012